Not much news coming out of this outfit. Can't be too many successes otherwise they would be making announcements. Have been reading some former reports and wondering if they've achieved what they said they were going to do.

2022 Annual report mentioned that CIBUS was expected to invest a further $4.2m - $4.5m within 20 months. Wondering if that came through? Also has their freeze drying capacity tripled as they said since 2022.

Think it was about this time last year that they invited shareholders out to the Rolleston site to look at the new facility, last years report said they would have Tawhiri 1 running early 2024 - interested to know if its generating revenue yet.

Chairmans report described the sale and lease back of Tawhiri 1 to the tune of $9m to enable Tawhiri 2 to commence. I drove past the site a month or so ago - doesn't look like anything has been done - looks like a storage shed missing its sides so no change since the chairmans report.

2023 was supposed to see a new drier operational at Tawhiri 1 early Q4 2023 and another late Q4 2023.