Quote:
Both sites are working single shift, 12 hours each day, 6 days per week – currently we’re experiencing up to 65 hours of processing time each week, but it requires constant effort to forecast and manage plant shutdowns.
The nature of alluvial deposits means grade fluctuates daily but, over time, it’s reconciling closely with our exploration.....It has been a long winter (and not over yet), both sites are still leaving the bedding-down phase, and at least another month of full, unhindered operation is needed before we can announce sensible news.
But long story short – we believe our forecasts of consistent 100oz per week production by December are achievable.