sharetrader
Results 1 to 10 of 2400

Threaded View

  1. #10
    Senior Member
    Join Date
    Aug 2019
    Posts
    689

    Default

    https://www.nzherald.co.nz/business/...ectid=12355074
    While both the Government and Meridian pointed to the finality of the decision, analysts have speculated that constraints in the transmission network, which could force Meridian and Contact Energy to have to spill water from South Island hydro stations for several years, could set conditions for the closure to be delayed for several years.

    "Meridian has put a confidential proposal to NZAS with the objective of allowing NZAS to close down the smelter over a longer period of time - Meridian has proposed up to four years," the company told the NZX.

    "To date that proposal has not been accepted and Meridian's current expectation is that the smelter will close on 31 August 2021 as previously announced by NZAS."
    Last edited by tomm; 10-08-2020 at 11:39 AM.

Tags for this Thread

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •