https://www.nzherald.co.nz/business/...ectid=12355074
While both the Government and Meridian pointed to the finality of the decision, analysts have speculated that constraints in the transmission network, which could force Meridian and Contact Energy to have to spill water from South Island hydro stations for several years, could set conditions for the closure to be delayed for several years.
"Meridian has put a confidential proposal to NZAS with the objective of allowing NZAS to close down the smelter over a longer period of time - Meridian has proposed up to four years," the company told the NZX.
"To date that proposal has not been accepted and Meridian's current expectation is that the smelter will close on 31 August 2021 as previously announced by NZAS."